Compilation content of mine construction organization design

For the construction technology organization measures, refer to the individual project construction organization design and related documents.

The construction organization design generally consists of the specification, the attached table and the blue part of the drawing. The specific content varies with the type of construction organization.
        (1) Contents of the overall design of the construction organization of the mining area
        Content construction organization overall design of mine have mine profiles; mine construction preparation; mine construction; beneficiation plant construction; supporting mine construction project; optimization of mine construction sequence; mine construction organization and management; economic effect analysis.
        (2) Contents of construction organization design of single project (mine)
        The construction organization design content of the single project includes the preliminary design of the mine; the geology and hydrogeology of the mine; the preparation for construction; the construction plan and construction method; the general layout of the industrial site and the use of permanent engineering; the queuing and construction period of the three types of construction; construction Quality and safety technical measures; construction technology management. Among them, the technical conditions of mine construction, the construction layout of mine construction, the key lines and key projects of mines, the optimization of mine construction and construction plans, and the organization and management of mine construction should be elaborated.
        (3) Content of unit construction construction organization (construction technology organization measures)
        1. Project Overview
        The project overview includes the project location, use and engineering quantity, engineering structure characteristics and construction conditions. For example, the requirements of "four connections and one leveling" for construction conditions, materials and prefabricated component preparation, transportation conditions, labor conditions and living conditions; equipment characteristics of installation engineering.
        2. Geological and topographic conditions
        Geological and topographical conditions require more for mining projects. The main civil engineering projects are topography, engineering geology and hydrogeological conditions.
        3. Construction plan and construction method
        The unit construction construction organization design should carry out program comparison (including the introduction of new technology), determine the construction method and the used equipment, and arrange the construction auxiliary production system. For example, the construction work should have construction cycle charts and blasting charts (instructions), support methods and application requirements, construction equipment and mechanized operation lines, construction quality standards and measures, new technologies and new processes, auxiliary work contents, etc.; There should be a total construction process, main part of the project construction operation mode, special project measures and requirements. Quality standards and measures; installation engineering should have equipment basis and civil work arrangements and requirements, main equipment and supporting facilities, pipelines, Transportation engineering arrangement, production of main processing parts, hoisting method and equipment selection, arrangement, operation mode and labor organization, etc., as well as equipment handling and installation methods, equipment debugging methods and testing methods, equipment test operation methods, etc.
        4. Construction quality and safety technical measures
        In addition to the technical organization measures to ensure quality and safety in the construction method, the mine construction project should especially consider the use of disaster prevention measures and comprehensive dust prevention measures.
        5. Construction preparation work plan
        The construction preparation work plan includes technical preparation, site preparation, labor, materials and equipment, and equipment preparation.
        6. Construction schedule and economic and technical indicators
        It is required to combine the project contents, decompose the project, determine the construction sequence, and prepare the network plan or image progress chart.
        7. Drawings and Schedules
        Schedules include schedules, materials, construction equipment, machinery, labor, semi-finished products, etc., transportation schedules, main economic and technical indicators, etc.
        In addition to the illustrations in the manual, corresponding drawings, such as engineering location maps, engineering flats, sectional drawings (including material stacking, lifting equipment layout and wiring, earthmoving abandonment sites, etc.), work surface construction equipment layout Figure, through the geological prediction map of the formation, processing parts and so on.